Launch of the FrHyGe project

Underground hydrogen storage demonstrator, involving 17 European partners and coordinated by Storengy
Hydrogen symbol and european map

On 20 March 2024, the European consortium met for the official launch of the FrHyGe* project, supported and funded by the European Union through the Clean Hydrogen Partnership. This 43 M€ project aims to validate the underground storage of hydrogen in salt caverns on an industrial scale. The project will allow the deployment of an industrial demonstrator in Manosque, France, as well as the replication study on the Harsefeld site in Germany and more widely at a European scale.

*FrHyGE: Full qualification in France for large-scale HYdrogen underground storage and replication from Germany to all European countries

A large-scale demonstrator for underground hydrogen storage in Europe

The FrHyGe project has 4 objectives:

  • Converting a natural gas (or brine) salt cavern for hydrogen storage,
  • Demonstrating the feasibility of injection and withdraw 100 tonnes of hydrogen over cycles ranging from 1 hour to 1 week in the converted caverns at the Manosque site,
  • Studying the market penetration, the value chain and preparing for replication at other sites in France, Germany, and across Europe,
  • Assessing the environmental impact, safety, and regulations in preparation for deployment on the GeoH2 (Manosque) and SaltHy (Harsefeld) projects.

As part of the FrHyGe project, Storengy, the project coordinator, and its partners will carry out technical, economic, regulatory, environmental, and safety studies. They will establish a roadmap to deploy the process of conversion and creation of storage caverns as quickly as possible and thus contribute to the creation of a true European hydrogen storage and transport backbone.

With a total budget of 43 million euros, of which 20 million are funded by the Clean Hydrogen Partnership, this project opens up new prospects for the development of renewable hydrogen storage in Europe.

Project timetable

This project, launched on 1er March 2024, will run for several years:

  • 2024 – 2025 :
    • Studies and analyses for the implementation of the demonstrator at the Manosque site and the replicability of the technology at the SaltHy site (Harsefeld, Germany)
  • 2026 – 2027 
    • Construction period
  • 2027 – 2029 :
    • 100 injections and withdrawals from 2 caverns at the Géométhane site in Manosque
    • Studies and analyses of hydrogen reactions according to the pressures to which it is subjected
    • Comparison of predictions with theoretical results

Next, in the commercial operation phase, the two caverns in Manosque will allow the storage of 6,000 tonnes of hydrogen. In Harsefeld a storage capacity of 5,200 tonnes is planned.

"The project is supported by the Clean Hydrogen Partnership and its members."